Shaar Ha’amakim Reclamation System WSS for irrigation

Project details

The diversion of the route of Highway 6 – the Trans-Israel Highway made it necessary to move the treated wastewater and flood reservoirs to a new location, and thereby, in effect, create a new reclamation system. The new reclamation system includes treated wastewater reservoirs, flood reservoirs, pumping stations and WSS- water supply system.

Work details

  • A floodwater reservoir built underneath the kibbutz, with a capacity of up to 330,000 thousand cubic meters.
  • The treated wastewater reservoir with a HDPE covering constructed in accordance with the regulatory requirements, with a volume of 50,000 cubic meters was constructed to collect water from the Kishon conglomerate system the quality of the water collected was high enough to permit its use for irrigating all crops.
  • For the floodwater reservoir, the system includes 2 pumps:

  1. 120 m3/h
  2. 100 m3/h

Both pumps are planned for a pressure of 95 m.

  • Operational reservoir: 2 pumps of 500 m3/h for a pressure of 30 m.

The porject is based on:

Pumping stations
Pumping stations
Reservoirs
Reservoirs
Specifications and pipelines
Specifications and pipelines
Consultation with authorities on issues of expropriation and planning
Consultation with authorities on issues of expropriation and planning

Project info

Assigned workers

  • Tsafrir Sofer - Project manager
  • Yitzhak Kliger - Project manager
  • Ran Wissman - Palgey Maim planner
  • Avi Zwilling - Electricity planner
  • Gidi Zolkov - Construction engineer
  • Gil Saguy - Small reservoir planner
  • engineering firm - Eyal Engineers

Client details

Client name

  • Kibbutz Shaar Ha'amakim

Contact name

  • Moishele Cohen - kibbutz secretary

Phone

  • 050-5418810

Our Services

1
Planning and consultation for the project with Highway 6, to obtain the appropriate compensation
2
Implementation in practice of the two reservoirs, irrigation infrastructures, pumping stations and pipelines
3
Close On-site supervision
4
Implementation work on of infrastructures for the fuel and gas lines adjacent to the reservoir - preparing the area for excavation and laying the pipes as required
5
Planning reservoir 2.5, including operational pond, internal and external reservoir drainage, specifications, and everything required for the agriculture delivery specification